How to get permission/approval for mobile tower erection from City Corporation(other than BBMP) in Karnataka?
Answered on May 05,2021
Name of the Department | CITY CORPORATION (Other than BBMP) |
Name of the Service | Permission / Approval for Mobile Tower Erection |
Whom to approach for this service (Designated Officer)? | Assistant Executive Engineer / Executive Engineer |
Procedure involved to get this service |
1) Application to be submitted online along with necessary documents by Citizen 2) Verifying the documents and forwarding to the Revenue Section. 3) Revenue section will verify the documents and forward to Engineering Section. 4) Based on Engineer report, Commissioner will approve the application. 5) Engineer will enter the fees and System will automatically intimate fee details to citizen through SMS 6) Citizen will pay the fees through Online. 7) Case Worker Will verify the Fees payment details and Forward to Commissioner. 8) Commissioner will approve based on the report. 9) Citizen can download DSC approved copy through online |
Who are eligible to get this service | Telecommunication Service Providers |
Fee/Charges to be paid to get the service | As fees fixed in the City Corporation |
Maximum number of days to wait to get this service delivered | 30 Working Days |
Whom to approach as a appeal (Competent Officer), if the service is not delivered in time or rejected by officer | Zonal Commissioner / Deputy Commissioner (Development) |
Maximum number of days to wait to get the decision of the Competent Officer | 15 Working Days |
Whom to approach as 2nd appeal (Appellate Authority), if the decision of the Competent officer is not acceptable or not implemented? | Commissioner |
Maximum no. of days to wait to get the decision of Appellate Authority | 30 Working Days |
Work Flow
Step |
Description |
No. of Days |
Designation |
1 |
Application to be submitted online along with necessary documents by citizens |
0.00 |
Others |
2 |
Case worker should verify documents and application details and forward it to revenue section |
2.00 |
Case Worker |
3 |
Revenue section will verify the documents and forward it to the town planning office |
5.00 |
Revenue Engineer |
4 |
ULB engineers will do the spot inspection and with report application forwarded to the commissioner |
10.00 |
Others |
5 |
Based on the report commissioner will approve the application and SMS sent to applicant for the fee payment |
5.00 |
Commissioner |
6 |
Applicant will pay the fee through online |
5.00 |
Others |
7 |
Case worker will verify the fee payment details and forward to commissioner |
1.00 |
Case Worker |
8 |
Commissioner will approve the application |
2.00 |
Commissioner |
9 |
Applicant can download the approved permission/approval copy through online. |
0.00 |