Home |BESCL |
How to give application for additional load/ new connection for FTNC additional load upto 7.5 KW for LT2 and LT3 in Bengaluru?
How to give application for additional load/ new connection for FTNC additional load upto 7.5 KW for LT2 and LT3 in Bengaluru?
Sakala Mission, Government of Karnataka
Answered on May 05,2021
Answered on May 05,2021
Name of the Department | BENGALURU ELECTRICITY SUPPLY COMPANY LIMITED |
Name of the Service | Application for Additional Load/ New Connection |
Name of the Sub Service | FTNC additional load upto 7.5 KW for LT2 and LT3 |
Whom to approach for this service (Designated Officer)? | Asst Executive Engineer |
Procedure involved to get this service | Services will be provided within 30 working days only after Payment of specified charges by the consumer. |
Who are eligible to get this service | bescom consumers |
Fee/Charges to be paid to get the service | Refer demand charges sheet published in BESCOM website |
Maximum number of days to wait to get this service delivered | 30 Working Days |
Whom to approach as a appeal (Competent Officer), if the service is not delivered in time or rejected by officer | Executive Engineer |
Maximum number of days to wait to get the decision of the Competent Officer | 7 Working Days |
Whom to approach as 2nd appeal (Appellate Authority), if the decision of the Competent officer is not acceptable or not implemented? | Superintending Engineer |
Maximum no. of days to wait to get the decision of Appellate Authority | 7 Working Days |
Website (if online) |
www.bescom.org |
Guide
  Click here to get a detailed guide
Karnataka Voter List 2024 - Search By Name, Download
Empowering citizens to exercise their democratic rights is crucial, especially in the vibrant state of Karnataka. This concise guide offers clear steps for downloading the voter list, searc..  Click here to get a detailed guide