How to give application for LOAD enhancement from 1 KW to 2 KW for Domestic Meter in BESCOM? Currently one broker is charging me for 8K for one meter


Sakala Helpline Sakala Helpline verified
Answered on April 01,2024

Name of the Service: Application for Additional Load/ New Connection

Name of the Sub Service: FTNC additional load upto 7.5 KW for LT2 and LT3

Whom to approach for this service (Designated Officer)?: Asst Executive Engineer

Procedure involved to get this service: Services will be provided within 30 working days only after Payment of specified charges by the consumer.

Who are eligible to get this service: Bescom Consumers

Fee/Charges to be paid to get the service: Refer demand charges sheet published in BESCOM website

Maximum number of days to wait to get this service delivered: 30 Working Days

Whom to approach as a appeal (Competent Officer), if the service is not delivered in time or rejected by officer: Executive Engineer

Maximum number of days to wait to get the decision of the Competent Officer: 7 Working Days

Whom to approach as 2nd appeal (Appellate Authority), if the decision of the Competent officer is not acceptable or not implemented?: Superintending Engineer

Maximum no. of days to wait to get the decision of Appellate Authority: 7 Working Days

Other information Website (if online): www.bescom.org

How would you rate the answer?


Excellent Good Neutral Poor Bad

Thank you for your response..


tesz.in
Hey , can you help?
Answer this question

Guide

Karnataka Voter List 2024 - Search By Name, Download

Empowering citizens to exercise their democratic rights is crucial, especially in the vibrant state of Karnataka. This concise guide offers clear steps for downloading the voter list, searc..
  Click here to get a detailed guide