I have done the saura model 3 registration on 26th jan 2021 1. When wiill be the next developer selection scheduled ? 2. I am from palakkad, will the developer selection will be specific to a region or will be common for all region? 3. Approx time required for installation completion from date of developer selection? 4. I read from news paper new tenders called for this, is this process completed and does it have any impact on next developer selection schedule?


1. Next phase of developer selection is getting delayed due to covid restrictions. It is expected during June-2021

2. Common to all region

3. 6 months