I registered for kseb soura phase 2 on Jan 6th. And the site is now showing developer selection is over for phase 2 but we didn't get any option for developer selection. What should we do ?
I registered for kseb soura phase 2 on Jan 6th. And the site is now showing developer selection is over for phase 2 but we didn't get any option for developer selection. What should we do ?
Kerala State Electricity Board, Government of Kerala
Answered on January 20,2021
Answered on January 20,2021
Developer selection completed recently. Next phase during March-April 2021.
Related Questions
-
Kerala State Electricity Board
Government of Kerala . Answered on January 19,2021Is developer selection Phase 2 soura scheme over as shown in KSEB site. When can we apply for next phase ?
Next phase will be during March- April 2021.
1 0 224 -
Kerala State Electricity Board
Government of Kerala . Answered on February 23,2021I have applied for Soura Subsidy project - MODEL II by paying application fee of 1000/- on Feb 21-2021. My application status is showing 'processed'. By when can I expect site inspection, project completion?
Site inspection will be conducted only after next round of Developer selection during April
1 0 168 -
Kerala State Electricity Board
Government of Kerala . Answered on March 19,2021I have registered for Soura Subsidy Project Model 2 by paying the application fee in the month of Dec 2020. I have selected the developer also. Unfortunately, nobody has responded yet. What should I do ?
Sir, you are not shortlisted for this phase. Please wait for next phase of developer selection, which is expected ...
1 0 92 -
Kerala State Electricity Board
Government of Kerala . Answered on March 19,2021I have registered under kseb soura model 2 on 26th jan 2021. When can I expect the developer selection to be opened for next phase ?
May 2021
1 0 83 -
Kerala State Electricity Board
Government of Kerala . Answered on April 07,2021I have registered for KSEB's Soura scheme Model II, I have paid for the existing meter, 1) will it be replaced by net-meter - how much have to pay if not renting 2) how is fixed charge calculated for soura consumers (e.g if consumption is less than export) 3)is there facility in inverter that can alert kseb office in cases of low energy production
1. Existing meter will be replaced with Net meter2. Fixed charge is based on net import. Tariff fixed by ...
2 0 650 -
Kerala State Electricity Board
Government of Kerala . Answered on April 21,2021I have applied soura model 2 on 15th December 2020 and Developer selectected successfully (Kondass automation). But till today there is no communication from anywhere. Let me know the Status of Soura project ?
You are not shortlisted for the project. Next round of Developer selection will be done during May-2021. Please select ...
1 0 66 -
Kerala State Electricity Board
Government of Kerala . Answered on May 24,2021I have done the saura model 3 registration on 26th jan 2021 1. When wiill be the next developer selection scheduled ? 2. I am from palakkad, will the developer selection will be specific to a region or will be common for all region? 3. Approx time required for installation completion from date of developer selection? 4. I read from news paper new tenders called for this, is this process completed and does it have any impact on next developer selection schedule?
1. Next phase of developer selection is getting delayed due to covid restrictions. It is expected during June-2021 2. Common ...
1 0 88 -
Kerala State Electricity Board
Government of Kerala . Answered on July 07,2021Applied for the KSEB soura scheme in January. Nothing happened till now, no developer selection, site inspection etc. Will something happen in the near future?
เดเต เดเดธเต เด เดฌเดฟเดฏเตเดเต เดชเตเดฐเดชเตเดชเตเดฑ เดธเตเดฐเตเตผเดเตเด เดชเดฆเตเดงเดคเดฟเดฏเดพเดฏ 'เดธเตเดฐ' เดธเดเดฌเดจเตเดงเดฟเดเตเด เดตเดฟเดตเดฐเดเตเดเตพ เดเดฐเดพเดฏเดพเดจเตเด เดธเดเดถเดฏเดเตเดเตพ เดฆเตเดฐเตเดเดฐเดฟเดเตเดเดพเดจเตเด เดชเตเดฐเดตเตเดคเตเดคเดฟ เดฆเดฟเดตเดธเดเตเดเดณเดฟเตฝ เดฐเดพเดตเดฟเดฒเต 10 เดจเตเด เดตเตเดเตเดเตเดเต ...
1 0 105 -
Kerala State Electricity Board
Government of Kerala . Answered on July 28,2021I have registered under the KSEB soura scheme II. How do I know whether I have been selected. I had also paid the registration charges. That has been now adjusted in my monthly power bill. There is no communication regarding the solar registration so far.
https://ekiran.kseb.in/ เดเดจเตเดจ เดตเตเดฌเตเดธเตเดฑเตเดฑเต เดตเดดเดฟเดฏเต 9496018370, 9496266631 เดเดจเตเดจเต เดจเดฎเตเดชเดฐเตเดเดณเดฟเดฒเต เด เดจเตเดตเตเดทเดฟเดเตเดเดฑเดฟเดฏเดพเตป เดเดดเดฟเดฏเตเด
1 0 2863 -
Kerala State Electricity Board
Government of Kerala . Answered on August 11,2021May I know what is the present status of kseb soura scheme installation based on my KSEB consumer number or soura register number?
You can have the details from KSEB Ekiran Also you may please call : 94962 66631 / 94960 18370
1 0 147 -
Kerala State Electricity Board
Government of Kerala . Answered on October 04,2021I have applied soura model 2 on 15th December 2020 and Developer selected successfully (Kondass automation). But till today there is no communication from anywhere. Let me know the Status of Soura project ? If I am not selected why is my payment not refunded yet.
You may please visit ekiran.kseb.in for more details
1 0 47 -
Kerala State Electricity Board
Government of Kerala . Answered on November 08,2021If I have an offgrid solar power plant installed in my home, can i apply for the kseb's sourya subsidy on-grid scheme?
No
1 0 171 -
Hrishikesh H K
Answered on September 02,2022I have registered for KSEB's Soura scheme Model II, I have paid for the existing meter, 1) will it be replaced by net-meter - how much have to pay if not renting 2) how is fixed charge calculated for soura consumers (e.g if consumption is less than export) 3)is there facility in inverter that can alert kseb office in cases of low energy production
I also feel the same. Even in single phase connection, voltage frequently goes below 180v. Will suggest KSEB to ...
2 0 364