Home | Guide | Government of Dubai Schemes and Processes |How to apply for approval of Public and Private Swimming Pool Drawings in Dubai?
How to apply for approval of Public and Private Swimming Pool Drawings in Dubai?
Written By Gautham Krishna
| Updated on January 29, 2023
This service enables you to obtain an approval on the drawings of private and public swimming pools in Dubai, according to the technical and engineering requirements and public safety standards in effect, and to the adopted filtration and disinfection systems, before starting the pool construction work.
Documents Required
- Engineering drawings of the swimming pools according to the requirements detailed in the Technical Guidelines Manual DM-HSD-GU34-ASPP2, along with owner signature on the project sheet.
How to apply for approval of Public and Private Swimming Pool Drawings in Dubai?
-
Login to Dubai Municipality website.
-
Apply for the service and upload the required Drawings.
-
Check Dubai Municipality's reply (Approved/Rejected/to be Amended or Completed) through the website.
-
Pay the due fees.
-
Receive the auto-stamped drawings approval through the website.
Time Required
- Instant
Fees Required
-
Private pools: AED 200
-
Public pools: AED 2,000
- Knowledge and Innovation fee: AED 20.
Terms & Conditions
- This service is mandatory, and consulting offices (for new buildings) and contracting companies (for adding a new pool to an existing building) must apply through the website.
- This service covers only the lands located under the Development Authority. For areas under the Building Permits Department, you should apply through Dubai Building Permit System BPS.
FAQs
What are some common queries related to Dubai Municipality?
You can find a list of common Dubai Municipality queries and their answer in the link below.
Dubai Municipality queries and its answers
You can find a list of common Dubai Municipality queries and their answer in the link below.
Dubai Municipality queries and its answers
Where can I get my queries related to Dubai Municipality answered for free?
Tesz is a free-to-use platform for citizens to ask government-related queries. Questions are sent to a community of experts, departments and citizens to answer. You can ask the queries here.
Ask Question
Tesz is a free-to-use platform for citizens to ask government-related queries. Questions are sent to a community of experts, departments and citizens to answer. You can ask the queries here.
Ask Question
When should the approval be obtained from Health and Safety Department and when it should be obtained from the Building Permits Department?
It is only one approval. For the Lands that belong to Dubai municipality، The plans should be submitted through the building permits system. For the lands that belong to the developers، the submission is made through Dubai Municipality website Dubai Municipality services. Public and private swimming pool plans approval service.
It is only one approval. For the Lands that belong to Dubai municipality، The plans should be submitted through the building permits system. For the lands that belong to the developers، the submission is made through Dubai Municipality website Dubai Municipality services. Public and private swimming pool plans approval service.
Can the pool owner obtain the approval directly without the need for a contractor?
All plans must be submitted through an approved contractor or consultant by the Building Permits Department.
All plans must be submitted through an approved contractor or consultant by the Building Permits Department.