How to request to Permit Modifications/Additions for Buildings in Dubai?
This service enables you to obtain a permit to carry out minor or major modifications and additions on existing buildings or under-construction projects.
Documents Required
- Building plans to be submitted as follows:
Initial approved plan and proposed plan marking the modifications as follows:
- Modifications location in yellow (on the approved plans).
- Modifications in red (on the proposed plans).
- Requested demolition work in green (on the approved plans).
- Plans of any other discipline that might be affected by the modifications (structural, electromechanical, sewage, thermal insulation, roads, civil defence).
How to request to Permit Modifications/Additions for Buildings in Dubai?
-
Login to Dubai Building Permit System
-
Apply for the service and fill the application.
-
Pay the due fees (except for first time applications).
-
Check Dubai Municipality's reply (Approved/ Rejected/To be Amended or Completed) through the BPS, within 3 working days from submission date.
-
Pay the due fees.
-
Receive the payment receipt through the website.
-
Receive the permit through the website.
Time Required
- 3 working days
Fees Required
Addition/Modification Permit:
- Application Fees: Free for the first time, then for every new application for all types of buildings as follows:
- Minor/medium modifications: AED 100
- Major/radical modifications: AED 200.
- Permit Fees: (Minor modifications after project completion):
- Total internal floor area: 30 fils/sqft.
- Exterior concrete walls: 10 fils/linear ft.
- Outdoor concrete slab: 10 fils/sqft.
- Outdoor Pergola area: 15 fils/sqft.
- Swimming pool areas and other external services: 30 fils/sqft.
Minor modifications/additions to existing buildings:
- Application Fees: Free for the first time then AED 100 for each new application
- Permit Fees:
- Private villas: AED 200
- Industrial and public service buildings: AED 300
- Multi-storey and floor area ratio buildings: AED 300.
Terms & Conditions
-
Minor modifications or additions do not include construction works or requirements related to parking lots, and have no impact on the design or the building use.
-
This permit is valid for 6 months from its issuance date, and has to be renewed if expired before the work starts on site.
-
The contractor must have an insurance policy for the construction works of modifications and additions with an area of (300) square meters or more.
FAQs
You can find a list of common Dubai Municipality queries and their answer in the link below.
Dubai Municipality queries and its answers
Tesz is a free-to-use platform for citizens to ask government-related queries. Questions are sent to a community of experts, departments and citizens to answer. You can ask the queries here.
Ask Question
You can send a general message in Dubai BPS system to (IT-Related system issue category).